Layer X
Case Study30 May 2026

Case Study: Combustion Nozzle in Inconel 625 — Consolidating 7 Parts into 1 for a Defence Supplier

A defence prime's combustion nozzle assembly had 7 brazed components and a 22-week procurement cycle. Layer X consolidated it into 1 DMLS Inconel 625 part. 72% fewer welds.

Layer X Team
4 min read
Share

The Challenge

A Hyderabad-based defence systems supplier manufacturing a gas generator unit for a pyrotechnic actuation system had a combustion nozzle assembly consisting of seven discrete components: a main body, three injector inserts, two retaining rings, and a convergent-divergent nozzle exit cone. The assembly required brazing and Inconel welding at four joints, creating 12 individual braze/weld quality points that each required NDT certification.

The procurement cycle for all seven components — machined from Inconel 625 billet — was 18–22 weeks. The brazing and welding operation added another 4–6 weeks. Total lead time from order to certified nozzle assembly: 24–28 weeks. The programme was supply-chain limited: nozzle assembly delivery was the longest-lead item in the entire actuation system.

The programme office tasked the supplier's engineering team to investigate whether additive manufacturing could compress the lead time while maintaining qualification equivalence to the existing design. Layer X in Ahmedabad was engaged for a DMLS design and build feasibility study.

Technical Requirements

  • Material: Inconel 625 (AMS 5666 chemistry, ELI requirements for trace elements)
  • Operating temperature: 650°C continuous, 900°C peak (2-second burn events)
  • Pressure: 180 bar operating, 270 bar proof test
  • All braze joints eliminated — equivalent strength through monolithic construction
  • NDT: Radiographic (X-ray) inspection of all walls > 1.5 mm; dye penetrant on all internal surfaces
  • Qualification: Mechanical properties (tensile, fatigue) to match AMS 5666 Inconel 625 bar requirements after heat treatment

Part Consolidation Design

The seven-component assembly was redesigned as a single monolithic DMLS part. Key design decisions:

Injector Geometry Integration

The three injector inserts (each separately brazed into the main body in the legacy design) were redesigned as integral internal passages with helical swirl geometry for combustion mixing. Internal helical channels at 35° swirl angle improved mixing efficiency by an estimated 12% versus the legacy straight-bore injectors — a benefit that emerged from the geometry freedom of DMLS that was not achievable in the brazed machined assembly.

Convergent-Divergent Nozzle Integration

The exit nozzle (previously a separate turned component welded to the main body) was printed integrally with the main body. The throat diameter (critical dimension: 8.5 mm ±0.05 mm) was printed at 8.8 mm and EDM wire-cut to final dimension — a hybrid machining approach that provided tighter tolerance control than the legacy turned-and-welded joint.

Lattice-Reinforced Wall Sections

The main body walls between the injector passages — a structurally complex region with competing stress fields from pressure load and thermal gradient — were redesigned with Altair Inspire topology optimisation. The resulting lattice web structure reduced mass in this region by 28% while maintaining equivalent structural performance under 180 bar pressure loading.

DMLS Build and Post-Processing

Inconel 625 was built at 20 µm layer height for maximum detail resolution in the internal injector passages. Build time: 31 hours. The build produced two units (one flight candidate, one destructive test article).

Post-processing sequence:

  1. Stress relief: 870°C for 1 hour in argon (per AMS 2801)
  2. HIP (Hot Isostatic Pressing): 1,175°C at 103 MPa for 4 hours — closes any sub-surface porosity to achieve >99.8% density
  3. Solution anneal: 1,150°C for 1 hour, water quench
  4. EDM wire-cut nozzle throat to 8.500 mm ±0.02 mm
  5. Electropolish internal injector passages (Ra from 12 µm to 1.8 µm)
  6. CMM inspection: 28 critical dimensions, all within drawing tolerances
  7. Radiographic inspection: No indications
  8. Dye penetrant inspection: No linear indications
  9. Tensile testing on companion test bars (from same build plate): UTS 860 MPa, Yield 510 MPa — both exceed AMS 5666 minimums

Results

MetricLegacy 7-part assemblyDMLS monolithic (Layer X)
Component count71 (monolithic)
Braze/weld joints120
NDT points requiring certification12 joints + volumeVolume only (no joints)
Lead time24–28 weeks8 weeks (design + build + HIP + test)
Mass1,240 g1,060 g (15% reduction)
Cost (per unit, 10+ run)₹1,85,000₹1,42,000 (23% reduction)
Programme critical pathNozzle assembly on critical pathRemoved from critical path

The monolithic DMLS nozzle passed all qualification tests (proof pressure, hot-fire testing at 180 bar for 10 burn cycles) and was accepted into the qualification database for the programme. The supplier reduced their nozzle assembly supply chain risk by eliminating four external suppliers (three machining vendors + one brazing vendor) and replacing them with a single Layer X production order.

Key Learnings

Part consolidation is the most powerful economic and risk-reduction lever in DMLS. Every eliminated joint eliminates: a separate machined component, a brazing or welding operation, an NDT inspection point, and a supplier qualification requirement. For assemblies with complex internal geometry and high-temperature requirements, Inconel 625 DMLS consistently delivers consolidation ratios of 3–8× with lead time reductions of 60–75%.

Contact Layer X Ahmedabad to discuss part consolidation opportunities in Inconel, Ti-6Al-4V, or stainless steel for your aerospace, defence, or energy application.

Further Reading

Start a project

Need a quote for your next project?

Upload your CAD file and get a precision manufacturing quote within 24 hours.

Get a Quote
More from Case Study

Continue reading

Case Study

Case Study: 250-Unit PA12 Switch Enclosures — From Approved Design to Dispatch in 5 Days

A Mumbai electronics distributor needed 250 custom switch enclosures in PA12 SLS for a customer delivery. Layer X produced, finished, and dispatched the full batch in 5 working days.

Read article
Case Study

Case Study: Custom Drone Frame in PA12-CF SLS — 43% Lighter Than Aluminium Extrusion

An Ahmedabad UAV startup needed a custom multirotor frame that was lighter than aluminium, printable in small batches, and ready for rapid design iteration. PA12-CF SLS delivered.

Read article
Case Study

Case Study: Gold Jewellery via SLA Castable Resin — Pattern Cost Reduced from ₹1,800 to ₹95

A Surat jewellery manufacturer was paying ₹1,800 per CNC wax pattern. SLA castable resin at Layer X produces the same pattern for ₹95 with faster turnaround. Full process breakdown.

Read article